Contract No: HK/2009/05

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 1)

 

Environmental Permit no. EP-364/2009/A,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEP-07/364/2009/A

 

Monthly Environmental Monitoring & Audit Report

 

- October 2011 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

14 November 2011


Table of contents          

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 8

1.1        Scope of the Report 8

1.2        Structure of the Report 8

2.     Project Background. 10

2.1        Background. 10

2.2        Scope of the Project and Site Description. 10

2.3        Division of the Project Responsibility. 11

2.4        Project Organization and Contact Personnel 12

3.     status of regulatory compliance. 17

3.1        Status of Environmental Licensing and Permitting under the Project 17

4.     Monitoring Requirements. 27

4.1        Noise Monitoring. 27

4.2        Air Monitoring. 28

5.     Monitoring Results. 31

5.1        Noise Monitoring Results. 31

5.2        Real Time Noise Monitoring Results. 33

5.3        Air Monitoring Results. 34

5.4        Waste Monitoring Results. 36

6.     Compliance Audit. 40

6.1        Noise Monitoring. 40

6.2        Real Time Noise Monitoring. 40

6.3        Air Monitoring. 40

6.4        Review of the Reasons for and the Implications of Non-compliance. 41

6.5        Summary of action taken in the event of and follow-up on non-compliance. 41

7.     Cumulative Construction Impact due to the Concurrent Projects. 41

8.     Environmental Site Audit. 44

9.     Complaints, Notification of Summons and Prosecution. 48

10.    Conclusion. 49


lIST OF TABLES

 

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Table 3.3      Summary of submission status under FEP-03/364/2009

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. 04/HY/2006

Table 3.5      Summary of submission status under FEP-04/364/2009/A

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.7      Summary of submission status under FEP-02/364/2009

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.9      Summary of submission status under FEP-01/364/2009

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.11    Summary of submission status under FEP-05/364/2009/A

Table 3.12    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.13    Summary of submission status under FEP-06/364/2009/A

Table 3.14    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 3.15    Summary of submission status under FEP-07/364/2009/A

Table 4.1      Noise Monitoring Stations

Table 4.2      Real Time Noise Monitoring Stations

Table 4.3      Air Monitoring Stations

Table 5.1      Noise Monitoring Stations for Contract no.  HY/2009/17

Table 5.2      Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006

Table 5.3      Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.4      Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.5      Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.6      Real Time Noise Monitoring Stations for Contract no. HY/2009/17

Table 5.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.8      Air Monitoring Station for Contract no. HY/2009/17

Table 5.9      Air Monitoring Stations for Contract no. HY/2009/18

Table 5.10    Air Monitoring Station for Contract no. HK/2009/01

Table 5.11    Air Monitoring Station for Contract no. HK/2009/02

Table 5.12    Air Monitoring Station for Contract no. HY/2009/15

Table 5.13    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.14    Details of Waste Disposal for Contract no. HY/2009/17

Table 5.15    Details of Waste Disposal for Contract no. 04/HY/2006

Table 5.16    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.17    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.18    Details of Waste Disposal for Contract no. HY/2009/18

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.20    Details of Waste Disposal for Contract no. HY/2009/19

Table 8.1      Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.2      Summary of Environmental Inspections for Contract no. HY/2009/18

Table 8.3      Summary of Environmental Inspections for Contract no. HY/2009/19

Table 8.4      Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.5      Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.6      Summary of Environmental Inspections for Contract no. HY/2009/17

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

lIST OF FIGUREs

 

Figure 2.1              Project Layout

Figure 2.2              Project Organization Chart

Figure 4.1              Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1         Environmental Mitigation Implementation Schedule

Appendix 4.1         Action and Limit Level

Appendix 4.2         Copies of Calibration Certificates

Appendix 5.1         Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2         Noise Monitoring Results and Graphical Presentations

Appendix 5.3         Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4         Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1         Event Action Plans

Appendix 6.2         Notification of Exceedance

Appendix 9.1         Complaint Log

Appendix 10.1      Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report – October 2011 specific for Environmental Permit no. EP-364/2009/A, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-03-364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2009/05 –Wanchai Development Phase II and Central Wanchai Bypass. This report presents the environmental monitoring findings and information recorded during the period 28th September 2011 to 27th October 2011. The cut-off date of reporting is at 27th of each reporting month.

 

  1. In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

 

·          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  - Central Interchange under FEP-05/364/2009/A

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Installation of couplers, cable detection, trial trench and pre-drilling in CR3

·          Site investigation and pre-drilling works

·          Diaphragm wall construction

·          Hoarding erection

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

 

·          Construction works were completed and surrendered on 11 Feb 2011

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

·          Pre-drilling works for Area 3.

·          Diaphragm wall construction works for CWB (stage 1) and SCL Protection Works

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·          Tunnel bored pile works at WCR1 area.

·          Diaphragm wall construction at WCR1 area.

·          Toe grout at WCR1 area.

·          Shear pin at WCR1 area.

·          Pumping test wells at WCR1 area.

·          King Post at WCR1 area.

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·          Seawall block construction, reclamation work and diaphragm wall construction preparation works at TS4

·          Diaphragm wall construction at TS1 and TPCWAE

·          Night time protection works at CHT

·          Construction of dewatering well at Hung Hing Road and POC

·          Precautionary works at Abutment A

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·          Marine Pre-drilling

·          Remove existing dolphin

·          Preparation works  and removal of existing marine piles

·          Set up of Contractor’s site office at Oil Street

·          Road works at Watson Road

·          Fabrication of bored piling platform

·          Bored piling

·          Ground contamination  assessment

·          Pre-drilling works for bored pile and Diaphragm wall

·          D-wall Pretreatment

·          Construction of Guide Wall

 

Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w – International Finance Centre Eastern and Western End of Podium on a weekly basis. Two limit level exceedances were recorded at M1a - Harbour Road Sports Centre on 7 and 25 October 2011 during restricted hour. After checking contractors’ work schedules and investigation found that no construction works were conducted and traffic noises as major noise sources contributed in the noise monitoring. Moreover, one limit level exceedance was recorded at M7e - International Finance Centre (Eastern End of Podium) on 11 October 2011 during day time. After checking contractors’ work schedules and investigation found that construction works were conducted as the major noise sources contributed in the noise monitoring. It was considered that the exceedances were not related at M1a but related at M7e. Also, no action level exceedance was recorded in this reporting month.

 

  1. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2 – Tunnel (North Point Section) and Island Eastern Corridor Link. No monitoring was conducted during the mentioned periods. Also, no project related action and limit level exceedance was recorded in the reporting period.

 

 

Air Monitoring

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b - Oil Street Community Liaison Centre; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a – Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w – International Finance Centre eastern and western wing on every six days basis. No action and limit level exceedance were recorded in the reporting period. The monitoring station was temporary suspension until obtainment of a representative long-term air monitoring station on 18 September 2011. Inspection for new location searching was conducted during October 2011.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was one environmental complaint received on 14 October 2011. No further complaint was received after follow-up action and investigation in this reporting month.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02 in this reporting period. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

 

Future Key Issues

  1. In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

 

·          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

 

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Installation of couplers, cable detection, trial trench and pre-drilling in CR3

·          Site investigation and pre-drilling works

·          Diaphragm wall construction

·          Hoarding erection

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

 

·          Construction works were completed and surrendered on 11 Feb 2011

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

·    Diaphragm wall construction works for both CWB and SCL Protection Works within HKCEC 1.

·    Site investigation works at north bank of HKCEC water Channel (from CH 200to CH260).

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·    Tunnel bored pile and diaphragm wall construction works.

·    Toe grout, Shear pine, Pumping test and King Post at WCR1 area.

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·    Diaphragm wall construction preparation works at TS4

·    Diaphragm wall construction at TS1 and TPCWAE

·    Night time protection works at CHT

·    Construction of dewatering well at Hung Hing Road and POC

·    Precautionary works at Abutment A

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

·    Preparation works  and removal of existing marine piles

·    Pre-drilling works for bored pile and Diaphragm wall

·    Marine Pre-drilling

·    Remove existing dolphin

·    Set up of Contractor’s site office at Oil Street

·    Road works at Watson Road

·    Fabrication of bored piling platform

·    Bored piling

·    Ground contamination  assessment

·    Pre-drilling works for bored pile and Diaphragm wall

·    D-wall Pretreatment

·    Construction of Guide Wall

·    D-wall and Barrette Piling

·    Sheet piling for Box Culvert T

·    Construction works for Box Culvert T

 

Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period 28th September to 27th October 2011. The cut-off date of reporting is at 27th of each reporting month.

 

1.2               Structure of the Report

 

Section 1         Introduction – details the scope and structure of the report.

 

Section 2         Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3         Status of Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4         Monitoring Requirements – summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5         Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 6         Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7         Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8         Site Inspection – summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9         Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

Project Background

2.1               Background

2.1.1.        “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        Design and Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.         The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

·          A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

·          The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

·          Tunnel control buildings and ventilation buildings;

·          Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

·          Associated road lighting, road signing, traffic control and surveillance system; and

·          Other associated works.

 

2.2.3.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        In the reporting month, Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) was commenced on 13 July 2011. The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central – Wan Chai Bypass (CWB) – Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

HK/2009/01

Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

13 July 2011

HY/2009/19

Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer for CWB

Principal Resident Engineer

Mr. Peter Poon

3916 1818

3529 2829

Lam Woo & CO., LTD.

Contractor under Contract no. HY/2009/17

Project Manager

Mr. K. S. Law

9090 1378

2566 7522

Site Agent

Mr. Tony Au

 

9725 5874

Sub Agent

Mr. Johnny Wong

9725 5870

Chiu Hing Construction & Transportation Co. Ltd.

Contractor under Contract no. 04/HY/2006

Contract Manager

Mr. Frederick Tsui

2967 6363

2967 6366

Senior Site Agent

Mr. Alvin Ma

2967 6363

2967 6366

Environmental Consultant

Mr. Jimmy Cheng

2965 0898

2556 9172

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Site Agent

Mr. Paul Yu

9456 9819

2634 1626

Operation Manager

Mr. Lau Yee Ching

9466 3918

Construction Manager

Mr Jerry Siu

9493 3664

Construction Manager

Mr Ricky Lai

9487 6549

Construction Manager

Mr KK Yuen

3498 1213

Environmental Officer (Compliance Manager)

Mr. Andy Mak

9103 2370

Environmental Supervisor

Ms. Kiwi Chan

6227 8840

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Chan Sing Cho

3658-3002

2827 9996

Site Agent

Mr. Mak Kam Wing

3658-3044

Deputy Site Agent

Mr. Anthony Wu

3658-3004

Quality & Environmental Manager

Mr. C.P. Ho

3658-3000

Environmental Officer

Ms Flora Ng

 

3658-3064

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HY/2009/19

Project Manager

Mr. Rayland Lee

3758 8879

2570 8013

Site Agent

Mr. Cheung Kit Cheung

6909 1555

Environmental Engineer

Mr. Simon Wong

9281 4346

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Brian Gillon

2214 7700

2140 6799

Deputy Site Agent

Mr. Desmond Sze

2214 7703

Environmental Officer

Mr. Anfernee Chow

2214 7721

Environmental Supervisor

Mr. Dennis Yu

2214 7738

Environmental Supervisor

Ryan Tsui

2214 7705

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Manager

Mr. M Y Wong

2823 7879

2566 2192

Site Agent

Mr. P J Fan

3557 6368

Head of construction

Mr. Roger Cheung

3557 6371

Environmental Officer

Mr. Daniel Sin

3557 6215

Environmental Supervisor

Mr. Kelven Yip

3557 6347

Environmental Supervisor

Mr. Tim Fung

3557 6349

 

 

Environmental Supervisor

Mr. Hilda Lau

3557 6378

 

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.4.3.        In this reporting month, the principal work activities of individual contracts are included as follows:

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

·          Construction works were completed and surrendered on 11 Feb 2011

 

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

·          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB)  - Central Interchange under FEP-05/364/2009/A

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Installation of couplers, cable detection, trial trench and pre-drilling in CR3

·          Site investigation and pre-drilling works

·          Diaphragm wall construction

·          Hoarding erection

 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

·          Pre-drilling works for Area 3.

·          Diaphragm wall construction works for CWB (stage 1) and SCL Protection Works

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·          Tunnel bored pile works at WCR1 area.

·          Diaphragm wall construction at WCR1 area.

·          Toe grout at WCR1 area.

·          Shear pin at WCR1 area.

·          Pumping test wells at WCR1 area.

·          King Post at WCR1 area.

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·          Seawall block construction, reclamation work and diaphragm wall construction preparation works at TS4

·          Diaphragm wall construction at TS1 and TPCWAE

·          Night time protection works at CHT

·          Construction of dewatering well at Hung Hing Road and POC

·          Precautionary works at Abutment A

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·          Marine Pre-drilling

·          Remove existing dolphin

·          Preparation works  and removal of existing marine piles

·          Set up of Contractor’s site office at Oil Street

·          Road works at Watson Road

·          Fabrication of bored piling platform

·          Bored piling

·          Ground contamination  assessment

·          Pre-drilling works for bored pile and Diaphragm wall

·          D-wall Pretreatment

·          Construction of Guide Wall

2.4.4.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

·          Construction works were completed and surrendered on 11 Feb 2011

 

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

·          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Installation of couplers, cable detection, trial trench and pre-drilling in CR3

·          Site investigation and pre-drilling works

·          Diaphragm wall construction

·          Hoarding erection

 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

·    Diaphragm wall construction works for both CWB and SCL Protection Works within HKCEC 1.

·    Site investigation works at north bank of HKCEC water Channel (from CH 200to CH260).

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·    Tunnel bored pile and diaphragm wall construction works.

·    Toe grout, Shear pine, Pumping test and King Post at WCR1 area.

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·    Diaphragm wall construction preparation works at TS4

·    Diaphragm wall construction at TS1 and TPCWAE

·    Night time protection works at CHT

·    Construction of dewatering well at Hung Hing Road and POC

·    Precautionary works at Abutment A

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·    Preparation works  and removal of existing marine piles

·    Pre-drilling works for bored pile and Diaphragm wall

·    Marine Pre-drilling

·    Remove existing dolphin

·    Set up of Contractor’s site office at Oil Street

·    Road works at Watson Road

·    Fabrication of bored piling platform

·    Bored piling

·    Ground contamination  assessment

·    Pre-drilling works for bored pile and Diaphragm wall

·    D-wall Pretreatment

·    Construction of Guide Wall

·    D-wall and Barrette Piling

·    Sheet piling for Box Culvert T

·    Construction works for Box Culvert T

 

status of regulatory compliance

3.1               Status of Environmental Licensing and Permitting under the Project

 

3.1.1.        A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

  4 Aug 2010

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Valid

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Valid

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Valid

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

 

3.1.2.        Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

3.1.3.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.

Table 3.2    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

N/A

Valid

Notification of Works Under APCO

319348

13 Jul 2010

N/A

Valid

Discharge Licence

WT00007212-2010

5 Aug 2010

5 Aug 2010 – 31 Aug 2015

Valid

Registration as a Waste Producer

5213-151-L2608-05

13 July 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7010400

16 Mar 2010

N/A

Valid

 

Table 3.3    Summary of submission status under FEP-03/364/2009

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

18 September 2010

Conditions 2.7 and 2.8

Submission of works schedule and location plan

1 September 2010

Condition 2.9

Noise Management Plan

1 September 2010

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-04/364/2009/A for contract no. 04/HY/2006 are shown in Table 3.4 and Table 3.5.

Table 3.4    Cumulative Summary of Valid Licences and Permits under Contract no. 04/HY/2006

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

N/A

Valid

Notification of Works Under APCO

322225

7 Oct 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7005123

9 Mar 2007

N/A

Valid

 

 

 

 

 

 

Table 3.5       Summary of submission status under FEP-04/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

11 July 2010

Conditions 2.7 and 2.8

Submission of works schedule and location plan

11 July 2010 and

5 August 2010

Condition 2.9

Noise Management Plan

19 October 2010

Condition 2.10

Landscape Plan

26 November 2010

 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

3.1.5.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.6 and Table 3.7

Table 3.6    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

6 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0384-11

29 Apr 2011

27 May 2011 to 26  Nov 2011

Valid

 

GW-RS0680-11

22 Jul 2011

24 Jul 2011 to 19 Jan 2012

Valid

 

GW-RS0689-11

28 Jul 2011

29 Jul 2011 to 28 Jan 2012

Valid

 

GW-RS0832-11

7 Sep 2011

03 Sep 2011 to 02 Mar 2012

Valid

 

GW-RS0850-11

12 Sept 2011

14 Sept 2011 to 13 Mar 2012

Valid

 

GW-RS0851-11

12 Sept 2011

16 Sept 2011 to 15 Mar 2012

Valid

 

GW-RE0683-11

26 Sept 2011

20 Sept 2011 to 19 Oct 2012

Valid

 

GW-RE0716-11

28 Sept 2011

07 Oct 2011 to 29 Mar 2012

Valid

Discharge Licence

WT00006220-2010

18 Mar 2010

31 Mar 2015

Valid

 

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

 

Table 3.7    Summary of submission status under FEP-02/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

18 May 2011

Special Conditions, Clause 2.6

Environmental Management Organization Chart

18 May 2011

Special Conditions, Clause 2.6

Commencement Date of Works

25 Jun 2011

Special Conditions, Clause 2.9

Noise Management Plan

10 Jun 2011

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

3.1.6.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.8 and Table 3.9.

Table 3.8    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for piling equipment

PP-RS0011-11

27 April 2011

1 June 2011 to

30 Nov 2011

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0225-11

17 Mar 2011

31 Mar 2011 to 30 Sept 2011

Cancel

 

GW-RS0280-11

30 Mar 2011

31 Mar 2011 to 30 Sept 2011

Cancel

 

GW-RS0335-11

8 April 2011

11 Apr 2011 to 30 Sept 2011

Cancel

 

GW-RS0343-11

11 April 2011

25 Apr 2011 to 10 Oct 2011

Expire

 

GW-RS0369-11

21 April 2011

1 May 2011 to

31 Oct 2011

Valid

 

GW-RS0377-11

27 April 2011

1 May 2011 to

31 Oct 2011

Valid

 

GW-RE0311-11

4 May 2011

5 May 2011 to 31 Oct 2011

Valid

 

GW-RS0401-11

3 May 2011

18 May 2011 to 17 Nov 2011

Valid

 

GW-RS0414-11

3 May 2011

9 May 2011 to 8 Nov 2011

Cancel

 

GW-RS0423-11

9 May 2011

22 May 2011 to 21 Nov 2011

Valid

 

GW-RS0430-11

9 May 2011

16 May 2011 to 15 Nov 2011

Cancel

 

GW-RS0453-11

19 May 2011

23 May 2011 to 22 Nov 2011

Valid

 

GW-RS0458-11

17 May 2011

21 May 2011 to 20 Nov 2011

Cancel

 

GW-RS0461-11

19 May 2011

23 May 2011 to 22 Nov 2011

Valid

 

GW-RS0473-11

27 May 2011

01 May 2011 to 30 Nov 2011

Cancel

 

GW-RS0496-11

31 May 2011

07 Jun 2011 to 06 Dec 2011

Valid

 

GW-RS0502-11

8 Jun 2011

13 Jun 2011 to 12 Dec 2011

Valid

 

GW-RS0579-11

22 June 2011

17 July 2011 to 16 Jan 2012

Valid

 

GW-RS0645-11

18 July 2011

22 Jul 2011 to 21 Jan 2012

Cancel

 

GW-RS0649-11

22 July 2011

1 Aug 2011 to 31 Jan 2011

Valid

 

GW-RS0691-11

25 July 2011

27 July 2011 to 26 Jan 2011

Cancel

 

GW-RS0716-11

2 Aug 2011

12 Aug 2011 to 11 Feb 2012

Valid

 

GW-RS0722-11

2 Aug 2011

5 Aug 2011 to 5 Oct 2011

Expire

 

GW-RS0723-11

12 Aug 2011

15 Aug 2011 to 14 Feb 2012

Valid

 

GW-RS0833-11

8 Sept 2011

10 Sept 2011 to 4 Mar 2012

Valid

 

GW-RS0857-11

16 Sept 2011

6 Oct 2011 to  5 Apr 2011

Valid

 

GW-RE0710-11

30 Sept 2011

1 Nov 2011 to 30 Apr 2012

Valid

 

GW-RS0918-11

7 Oct 2011

10 Oct 2011 to 9 Apr 2012

Valid

 

GW-RS0929-11

7 Oct 2011

10 Oct 2011 to 9 Apr 2012

Valid

 

GW-RS0930-11

11 Oct 2011

1 Nov 2011 to 30 Apr 2012

Valid

 

GW-RS0931-11

7 Oct 2011

10 Oct 2011 to 9 Apr 2012

Valid

 

GW-RS0941-11

20 Oct 2011

23 Nov 2011 to 22 May 2012

Valid

 

GW-RS0955-11

14 Oct 2011

23 Nov 2011 to 22 May 2012

Valid

 

GW-RS0968-11

20 Oct 2011

18 Nov 2011 to 17 May 2012

Valid

 

GW-RS0983-11

24 Oct 2011

26 Oct 2011 to 23 April 2012

Valid

 

GW-RS0984-11

 25 Oct 2011

30 Oct 2011 to 27 April 2012

Valid

Discharge Licence

WT00006249-2010

22 Mar 2010

31 Mar 2015

Valid

WT00006436-2010

15 Apr 2010

30 Apr 2015

Valid

WT00006673-2010

14 May 2010

31 Mar 2015

Valid

WT00006757-2010

28 May 2010

31 May 2015

Valid

WT00007129-2010

28 July 2010

31 Jul 2015

Valid

WT00008982-2011

26 April 2011

30 April 2016

Valid

WT00009691-2011

1 Aug 2011

31 July 2016

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

Registration as Chemical Waste Producer (TKO 137)

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

 

Table 3.9    Summary of submission status under FEP-01/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

14 Jun 2011

Special Conditions, Clause 2.6

Environmental Management Organization Chart

14 Jun 2011

Special Conditions, Clause 2.6

Commencement Date of Works

21 Jun 2011

Special Conditions, Clause 2.9

Noise Management Plan

28 Jun 2011

Condition 2.11

Landscape Plan

23 Aug 2011

Condition 2.9

 

Noise Management Plan (Rev.A)

28-Sep-11

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

 

3.1.7.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.10 and Table 3.11.

Table 3.10  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Permit / Licence / Notification / Approval

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Permit issued

Valid

Notification of Works Under APCO

322293

07 Oct 2010

Notified

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0840-11

09 Sept 2011

09 Sept 2011 –
28 Oct 2011

Valid

 

GW-RS0878-11

22 Sept 2011

22 Sept 2011 –
28 Oct 2011

Valid

 

GW-RS0993-11

28 Oct 2011

28 Oct 2011 –
25 Apr 2012

Valid

Discharge Licence

WT00008229-2011

13 Jan 2011

31 Jan 2016

Valid

Registration as a Waste Producer

WPN: 8335-121-L1048-04

17 Dec 2010

Registration completed

Application for a Billing Account for Disposal of Construction Waste ( Construction Work Contract with Value of $1 million or Above) under the Waste Disposal Ordinance (Cap. 354) sections 5 & 9 of the Waste Disposal (Charges for Disposal of Construction Waste) Regulation.

Account No.: 7011587

11 Oct 2010

Account approved

Valid

 

Table 3.11  Summary of submission status under FEP-05/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

01 March 2011

Condition 2.10

Landscape Plan (Rev. 4)

3 August 2011

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

3.1.8.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.12 and Table 3.13

Table 3.12  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

N/A

Valid

FEP-06/364/2009/A

22 Nov 2010

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0749-11

11 Aug 2011

15 Aug 2011 to

7 Feb 2012

Valid

Construction Noise Permit (CNP) for Installation of Instrumentation at CHT

GW-RS0847-11

14 Sep 2011

19 Sep 2011 to

16 Mar 2012

Valid

Construction Noise Permit (CNP) for Diaphragm Wall Construction at TPCWAE

GW-RS0858-11

16 Sep 2011

18 Sep 2011 to

16 Mar 2012

Valid

Construction Noise Permit (CNP) for Diaphragm Wall Construction at TPCWAE (24 hr)

GW-RS0883-11

4 Oct 2011

5 Oct 2011to

4 Apr 2012

Valid

Construction Noise Permit (CNP) for Diaphragm Wall Construction at TS1

GW-RS0820-11

5 Sep 2011

8  Sep 2011 to

7 Mar 2012

Valid

Registration as a Chemical Waste Producer

WPN: 5213-147-C1169-35

15 Nov 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

27 Sep 2010 to 27 Jan 2016

Valid

Billing Account under Waste Disposal Ordinance (Dumping by Vessel)

7011761

28 Apr 2011

1 May 2011  to

30 Oct 2011

Valid

Water Discharge Licence (Discharge at  Portion VII)

WT00008780-2011

22 Mar 2011

22 Mar 2011 to 31 Mar 2016

Valid

Water Discharge Licence (Discharge at  Hung Hing Road)

WT00010482-2011

30 Sep 2011

30 Sep 2011 to 30 Sep 2013

Valid

 

Table 3.13  Summary of submission status under FEP-06/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

11 Mar 2011

Amendment for Management Organization of Main Construction Companies

16 May 2011

Condition 2.7

Works Schedule

15 Mar 2011

Condition 2.8

Location Plan

15 Mar 2011

Condition 2.23

Noise Management Plan

6 May 2011

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

3.1.9.        The current status on licences and/or permits on environmental protection pertinent and submission under FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.14 and Table 3.15.

Table 3.14  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

N/A

Valid

Notification of Works Under APCO

326160

24 Jan 2011

N/A

Valid

Registration as a Waste Producer

7012306

10 Feb 2011

N/A

Valid

Registration as Chemical Waste Producer

5213-151-C3654-01

24 Mar 2011

N/A

Valid

Application for Vessel Disposal

7012306

21 July 2011

N/A

Valid

 

Table 3.15  Summary of submission status under FEP-07/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

02 Jun 2011

Condition 2.13

Landscape Plan

7 July 2011

Monitoring Requirements

4.1               Noise Monitoring

Noise Monitoring Stations

4.1.1.        The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1.  Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1    Noise Monitoring Stations

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

 

Real time Noise Monitoring Stations

4.1.2.        Review of feasibility on the real time noise monitoring stations was conducted in July with IEC. Station, RTN1a, Tung Lo Wan fireboat Station was found not appropriate to be a monitoring station for monitoring the IECL Piling works and Demolition after visited. 

4.1.3.        The noise monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2    Real Time Noise Monitoring Stations

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

 

Noise Monitoring Parameters, Frequency and Duration

4.1.4.        The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.5.        Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.6.        Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

·          One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

·          One set of measurements between 2300 and 0700 hours on next day on everyday.

4.1.7.        If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.8.        As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.9.        Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

4.1.10.    The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements July be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.2               Air Monitoring

Air Quality Monitoring Stations

4.2.1.        The air monitoring stations for the Project are listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.3    Air Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point (Temporary Suspended)

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Garden opposite to Pedestrian Plaza

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (western End of Podium)

Central

Remarks: As per the ENPC meeting in March 2011, the monitoring stations CMA3a – Future CWB site office at Wanchai Waterfront Promenade was renamed as remark.

 

Air Monitoring Parameters, Frequency and Duration

4.2.2.        One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.        All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.        For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.        High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

·          0.6 – 1.7 m3 per minute adjustable flow range;

·          Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

·          Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

·          Capable of providing a minimum exposed area of 406 cm2;

·          Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

·          Equipped with a shelter to protect the filter and sampler;

·          Incorporated with an electronic mass flow rate controller or other equivalent devices;

·          Equipped with a flow recorder for continuous monitoring;

·          Provided with a peaked roof inlet;

·          Incorporated with a manometer;

·          Able to hold and seal the filter paper to the sampler housing at horizontal position;

·          Easily changeable filter; and

·          Capable of operating continuously for a 24-hour period.

 

4.2.6.        Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

4.2.7.        A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.        Filter paper of size 8” x 10” shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.9.        After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.10.    All the collected samples shall be kept in a good condition for 6 months before disposal.

4.2.11.    Current calibration certificates of equipments are presented in Appendix 4.2.

Monitoring Results

5.0.1.        The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.        In the reporting month, the concurrent contracts are as follows:

Ÿ         Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

Ÿ         Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

Ÿ         Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

Ÿ         Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009

Ÿ         Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre

Ÿ         Contract no. HK/2009/02 Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai East

5.0.3.        The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

5.1               Noise Monitoring Results

5.1.1.        The noise monitoring at stations were M1a and M5b during day time, M3a, M4b, M5b and M6 during restricted hour were rescheduled on 13 October 2011 due to rain.

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

5.1.2.        The proposed division of noise monitoring stations for Contract no. HY/2009/17 are summarized in Table 5.1 below:

Table 5.1    Noise Monitoring Stations for Contract no.  HY/2009/17

Station

Description

M4b

Victoria Centre

 

5.1.3.        No action and limit level exceedance was recorded during day time and restricted hour period in the reporting month. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2. 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

5.1.4.        Construction activity under contract no. 04/HY/2006 was completed, no noise monitoring for the contract was conducted. Noise monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2009/18 and 04/HY/2006 are summarized in Table 5.2 below:

Table 5.2    Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006

Station

Description

M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

 

5.1.5.      No action level and one limit level exceedance was recorded during day time on 11 October 2011 in the reporting month. After checking contractor’s work schedules and investigation found that Excavation by hydraulic extractor, drilling by drill rig and breaking works for TTA stage 3 in front of IFC were conducted during monitoring. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.  Details of the Notification of Exceedance can be referred in Appendix 6.2.

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.1.6.        The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.3 below.

Table 5.3    Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Station

Description

M1a

Harbour Road Sports Centre

 

5.1.7.        No action level and two limit level exceedances were recorded at M1a – Harbour Road Sports Centre due to a recorded noise complaint on 7 and 25 October 2011 during restricted hour for the contractor of HK/2009/02. Major noise source was contributed from Tonnochy Road and water sport competition at Wan Chai Training Swimming Pool. Details of the Notification of Exceedance can be referred in Appendix 6.2. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2 and the complaints can be referred in Appendix 9.1. 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.1.8.        The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was commenced on 13 July 2011. The proposed division of noise monitoring stations are summarized in Table 5.4 below.

 

Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

5.1.9.        No action level and limit level exceedance was recorded during day time and restricted hour period in the reporting month. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

 

5.1.10.    Noise monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.5 below.

Table 5.5    Noise Monitoring Stations for Contract no. HY/2009/19

Station

Description

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

5.1.11.    No action level and limit level exceedance was recorded during day time period. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2

5.2               Real Time Noise Monitoring Results

5.2.1.        No construction activity with valid Construction Noise Permit was conducted during night time period (2300 to 0700) in this reporting month.

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009 and Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

5.2.2.        The proposed division of noise monitoring stations are summarized in Table 5.6 below. Real time noise monitoring for the piling works under contract no. HY/2009/17 was commenced on 5 October 2010

Table 5.6    Real Time Noise Monitoring Stations for Contract no. HY/2009/17

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

Real time noise monitoring results and graphical presentation during night time period are for information only.

5.2.3.        No project related action and limit level exceedance were recorded in the reporting period. Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4 .

5.2.4.        The proposed division of noise monitoring stations are summarized in Table 5.7 below. Real time noise monitoring for major construction works under contract no. HY/2009/19 was commenced on 24 April 2011.

Table 5.7    Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

RTN2

North Point

Oil Street Community Liaison Center

Real time noise monitoring results and graphical presentation during night time period are for information only.

5.2.5.        No project related action and limit level exceedance were recorded in the reporting period. Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4 .

5.3               Air Monitoring Results

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

5.3.1          The proposed division of air monitoring stations are summarized in Table 5.8 below. Air monitoring for the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.

Table 5.8    Air Monitoring Station for Contract no. HY/2009/17

Station

Description

CMA2a

Causeway Bay Community Centre

5.3.2          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

5.3.3          Construction activity under contract no. 04/HY/2006 was completed, no air monitoring for the contract was conducted. Air monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.The proposed division of air monitoring stations are summarized in Table 5.9 below.

Table 5.9    Air Monitoring Stations for Contract no. HY/2009/18

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

 

5.3.4          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

5.3.5          The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on 25 August 2011. The proposed division of air monitoring stations are summarized in Table 5.10 below.

Table 5.10 Air Monitoring Station for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

5.3.6          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.3.7          The commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of air monitoring stations are summarized in Table 5.11 below.

Table 5.11 Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

5.3.8          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.3.9          The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air quality monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are summarized in Table 5.12 below.

Table 5.12 Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

5.3.10      The proposed division of air monitoring stations are summarized in Table 5.13 below. Air monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 26 April 2011.

Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil St Community Liaison Centre

CMA2a

Causeway Bay Community Centre

5.3.11      Since the land located the Oil Street Community Liaison Centre will be handed-over to Food and Environmental Hygiene Department (FEHD) for the construction of temporary FEHD depot by the end of September 2011, the air monitoring station – CMA1b was then removed on 18 September 2011 and is not available for the air quality monitoring in the existing location at Oil Street Community Liaison Centre. Owing to the rejection or no response from the nearby air sensitive receivers in allowing the implementation of impact air quality monitoring, CMA1b was proposed to be temporary suspension until obtainment of a representative long-term air monitoring station in last reporting month.

5.3.12      No exceedance was recorded at CMA2a in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

 

5.4               Waste Monitoring Results

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

5.4.1.        No Inert C&D waste was recycled in the reporting month. Details of the waste flow table are summarized in Table 5.14

Table 5.14  Details of Waste Disposal for Contract no. HY/2009/17

Waste Type

Quantity this month, m3

Cumulative Quantity-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

1354.82

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

N/A

N/A

N/A

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

5.4.2.        Construction works were completed and a duly signed report on Completion of Works was issued by the Engineer dated on 1 March 2011.  In addition, acknowledge of FEP surrender was under preparation by the Contractor. No inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.15.

Table 5.15  Details of Waste Disposal for Contract no. 04/HY/2006

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

1288.5

Chai Wan and

T.K.O. 137

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

 

Contract nos. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

5.4.3.        Inert and non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.16.

Table 5.16  Details of Waste Disposal for Contract no. HK/2009/01

Waste Type*

Quantity this month, m3

Cumulative-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

2507.68

4973.88

TKO137, TM38

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

39.82

107.52

SENT Landfill

Non-inert C&D materials recycled

4520

4979

N/A

Chemical waste disposed

100

1100

Kwun Kee (Chemical Waste Collector)

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.4.4.        Inert C&D & non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.17.

Table 5.17  Details of Waste Disposal for Contract no. HK/2009/02

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

8,047

50,018

TKO137, TM 38

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

25

41

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

1,104

N/A

Contractor clarified that no Inert and Non-inert C&D materials disposed in June 2011

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

 

5.4.5.        Inert C&D and non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.18.

Table 5.18  Details of Waste Disposal for Contract no. HY/2009/18

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

2034.7

6627.7

T.K.O. 137

Inert C&D materials recycled

NIL

58.5

N/A

Non-inert C&D materials disposed

15.6

185.7

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.4.6.        Inert & Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.19.

Table 5.19  Details of Waste Disposal for Contract no. HY/2009/15

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

330.0

2287.4

Tuen Mun Area 38

Inert C&D materials recycled

NIL

304

N/A

Non-inert C&D materials disposed

11.1

61.9

SENT Landfill

Non-inert C&D materials recycled

NIL

61.3

N/A

Chemical waste disposed

1,800

3,800

N/A

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

5.4.7.        Only Non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.20.

Table 5.20  Details of Waste Disposal for Contract no. HY/2009/19

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

630.954

630.954

N/A

Non-inert C&D materials disposed

4.938

7.741

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

0.034

0.034

N/A

Compliance Audit

6.0.1.        The Event Action Plan for construction noise, air qualities are presented in Appendix 6.1.

6.1               Noise Monitoring

 

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

6.1.1.        No exceednace was recorded in the reporting month.

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

6.1.2.        No noise monitoring was undertaken in the reporting month.

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

6.1.3.        No action level and one project related limit level exceedance was recorded on 11 October 2011 in the reporting month. Investigation found that Excavation by hydraulic extractor, drilling by drill rig and breaking works for TTA stage 3 in front of IFC were conducted during monitoring

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention Exhibition Centre – Tunnel Works under FEP-02/364/2009

 

6.1.4.        No exceednace was recorded in the reporting month.

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.1.5.        No action level and three limit level exceedance were recorded at M1a – Harbour Road Sports Centre on 7 and 25 October 2011 during restricted hour. Investigation found that major traffic noise was contributed in the noise monitoring and not related to the Project.

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

6.1.6.        No exceednace was recorded in the reporting month.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.1.1          No exceednace was recorded in the reporting month.

6.2               Real Time Noise Monitoring

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

6.2.1          No exceednace was recorded in the reporting month.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.2.2          No exceednace was recorded in the reporting month.

6.3               Air Monitoring

 

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

6.3.1.        No exceedance was recorded in the reporting month.

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

6.3.2.        No air quality monitoring was undertaken in the reporting month.

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

6.3.3.        No exceednace was recorded in the reporting month.

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

6.3.4.        No exceednace was recorded in the reporting month.

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.3.5.        No exceednace was recorded in the reporting month.

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A

6.3.6.        No exceednace was recorded in the reporting month.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.3.1          No exceednace was recorded in the reporting month.

6.4               Review of the Reasons for and the Implications of Non-compliance

6.4.1.        There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.4.2.        There was exceedance of noise level recorded during day time on 11 October 2011 at M7e that was considered in relation to the excavation, drilling and breaking during monitoring.

6.5               Summary of action taken in the event of and follow-up on non-compliance

6.5.1.        According to the Event and Action Plan stated in Appendix 6.1, repeated measurement for noise monitoring station (M7e) would be conducted immediately once Limit Level exceedance recorded in relation to Contract no. HY/2009/18, site investigations would be arranged accordingly to observe and record the sources of the exceedance(s). During the noise monitoring on 11 October 2011, excavation by hydraulic extractor, drilling by drill rig and breaking works for TTA stage 3 in front of IFC and no abnormal work were observed through out the period of noise monitoring. The extended acoustic lining on the top of noise barriers were not erected during operations. Contractor had suspended the works after received the notification on the same day to review the plant operations. Contractor explained that due to the Strong Monsoon Signal was in force during the monitoring, fully erection of the noise barriers were not practicable which follows their safety management plan. Additional monitoring was conducted on 13 October 2011 at 14:20. Excavation by hydraulic extractor operated with fully erected moveable noise barrier, drilling by drill rig and breaking works for TTA stage 3 in front of IFC were observed during noise monitoring.

6.5.2.        No further exceedance was recorded in the subsequent noise monitoring during non-restricted hours.  Nevertheless, the effectiveness of remedial actions implemented by the Contractor will be continuously reviewed.

7                     Cumulative Construction Impact due to the Concurrent Projects

7.0.1.        According to Condition 3.4 of the EP-364/2009/A, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.        From the Monthly EM&A report (September 2011) of Central Reclamation Phase III (CRIII) the key works in October 2011 are as follows:

·          Type A filling in FRAW and FRAE above +2.5mPD

·          General filling works above +2.5mPD in IRAE

·          Surcharging in FRAW and FRAE

·          Installation of removable panels at caisson

·          Installation of remaining seawall blocks and retaining wall on the west side of culvert F

·          Construction of storm and foul drainage and gullies in hinterlands for Road P2 and Road D9

·          Roadworks for Road P2

·          Construction of GPO boundary wall

·          Construction of PLA boundary wall and entrance

·          Construction of Promenade enhancement works

·          Construction of buildings at PLA berth

·          Road P2 Underpass structures

·          Construction of CWB structure

·          Backfilling and waterproofing works for CWB structure

·          Importation of fill material

·          Strengthening of Man Yiu Street Footbridge

7.0.3.        According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activity under Wan Chai Development Phase II were the filling works at NPR2E and HKCEC1, seawall block construction at TCBR1W, maintenance dredging of navigation channel and mooring area, HKCEC3w and marine bored piling at MTR Tunnel Crossing. Advanced piling works at FEHD Whitfield Depot, Central Interchange, cross-harbour water mains, tunnel works at WCR1, Diaphragm wall construction at Causeway Bay Typhoon shelter and marine pre-drilling in the reporting month. The major environmental impact was water quality impact at Causeway Bay and Wan Chai. Land-based construction activity were advance piling works at FEHD Whitfield Depot, sheet piling and pre-drilling works at Central, marine pre-drilling at North Point in the reporting month and tunnel works at Wan Chai East.

7.0.4.        The major environmental impacts generated from advanced piling works at FEHD Whitfield Depot were undertaken and sheet piling, pre-drilling and sheet piling works at Central and tunnel works at Wan Chai East in the reporting month. No significant air impact was anticipated in the reporting month. Notwithstanding, a project-related exceedance regarding construction noise was recorded during non-restricted hours referred to Contract no. HY/2009/18 in the reporting month.  In general, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II, and Central Reclamation Phase III was mainly insignificant.

8          Environmental Site Audit

8.0.1.        During this reporting month, weekly environmental site audits were conducted for Contracts no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02. No non-conformance was identified during the site audits.

8.0.2.        Four site inspections for Contract no. HY/2009/15 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.1.

Table 8.1    Summary of Environmental Inspections for Contract no. HY/2009/15

Item

Date

Observations

Action taken by Contractor

Outcome

111001_01

4-Oct-11

The contractor was reminded to tidy up the site entrance at Ex-Fire boat station as slimy overflow the mud pit at the area of piling

 tidy up the site entrance at Ex-Fire boat station.

Completion as observed on 11-OCt-11

111011_01

11-Oct-11

Clean water shall be used for wheel washing (portion 13, TS1)

Use clear water for wheel washing

Completion as observed on 18-OCt-11

111011_02

11-Oct-11

Floating refuses shall be collected (TS1)

Collect floating refuse

Completion as observed on 18-OCt-11

111011_03

11-Oct-11

Gaps between seawall blocks shall be filled by gap filter

fill the gaps between seawall blocks

Completion as observed on 18-OCt-11

111011_04

11-Oct-11

Hoarding shall be erected as soon as practicable (TS4)

Erect Hoarding

Completion as observed on 18-OCt-11

111011_05

11-Oct-11

Stockpile shall be covered by tarpaulin (TS4)

Covering the stockpile by tarpaulin

Completion as observed on 18-OCt-11

111018_01

18-Oct-11

Stockpile was observed stored outside the rock bund at TS4. The contractor was reminded filling for reclamation shall be conducted behind seawall.

Remove the stockpile outside the rock bund and conduct filling for reclamation behind seawall

Completion as observed on 25-OCt-11

111018_02

18-Oct-11

Slurry (muddy water) leakage was observed at the site entrance at TS1. Those muddy water shall be treated properly prior discharge.

Treated muddy water properly prior discharge

Completion as observed on 25-OCt-11

111025_01

25-Oct-11

Stockpile was observed exceed rock bund, the contractor should remove it. They also reminded again that filling for reclamation should behind seawall.

Conduct filling for reclamation behind seawall

Completion as observed on 1-Nov-11

 

8.0.3.        Five site inspections for Contract no. HY/2009/18 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.2.

Table 8.2    Summary of Environmental Inspections for Contract no. HY/2009/18

Item

Date

Observations

Action taken by Contractor

Outcome

30-Sep-11

110930_01

The contractor was reminded to collect and treat the silt water properly.

Collect and treat the silt water properly

Completion as observed on 6-OCt-11

6-Oct-11

111006_01

The enclosures of grouting plant and cement mixing plant shall be improved

Improve the enclosures of grouting plant and cement mixing plant

Completion as observed on 13-OCt-11

13-Oct-11

111013_01

Oil spillage was observed at Financial Street, the contractor should clear the oil with spill kit. Also, drip tray should be provided for chemical storage

Clear the oil with spill kit and provide drip tray should be  for chemical storage

Completion as observed on 20-OCt-11

20-Oct-11

111020_01

Drip trays shall be provided for chemical storage and bar fixing machine.

Provide drip tray should be  for chemical storage and bar fixing machine

Completion as observed on27-OCt-11

8.0.4.         Five site inspections for Contract no. HY/2009/19 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.3.

Table 8.3    Summary of Environmental Inspections for Contract no. HY/2009/19

Item

Date

Observations

Action taken by Contractor

Outcome

110928_01

28-Sep-11

The contractor was reminded to enclose the dust generation part of the cement mixing plant.

Enclose the dust generation part of the cement mixing plant

Completion as observed on 5-OCt-11

111019_01

19-Oct-11

The contractor was reminded to improve the concrete bunding in order to prevent the run off discharge outside the site area. (site entrance)

Improve the concrete binding in order to prevent the run off discharge outside the site area.

Completion as observed on 26-OCt-11

111019_02

19-Oct-11

Environmental Permits shall be posted at the site entrance after maintenance work.

Post Environmental Permits at the site entrance

Completion as observed on 26-OCt-11

111026_01

26-Oct-11

Oil leakage of excavator was observed. The contractor was reminded to repair it before use.

repair the disorder plants before use

Completion as observed on 2-Nov-11

111026_02

26-Oct-11

The oil contaminated top soil shall be treated as chemical waste.

Treat the top soil as chemical waste

Completion as observed on 2-Nov-11

8.0.5.        As construction works for Contract no.04/HY/2006 were completed, no site inspection was carried out since February 2011. 

8.0.6.        Five site inspections for Contract no. HK/2009/01 was carried out during this reporting period as the commencement date of the project was on 25 August 2011.

Table 8.4    Summary of Environmental Inspections for Contract no. HK/2009/01

Item

Date

Observations

Action taken by Contractor

Outcome

110928_01

22-Sep-11

Sand bags at the edge of HKCEC site boundary shall be enhanced.

Providing the sand bags at the edge of HKCEC site boundary

Completion as observed on 4-Oct-11

111012_01

12-Oct-11

Silty water was observed at sedimentation tank at TST. Contractor was reminded to slow down the flow rate or other measures so as to settle the sediment

Slowing down the flow rate of the water discharge

Completion as observed on 20-Oct-11

111012_02

12-Oct-11

Silt curtain at jetty barge shall be repaired. Besides, the filling material at the walkway of barge shall be removed

Removal of the fill material at walkway and maintenance of the silt curtain

Completion as observed on 20-Oct-11

111020_01

20-Oct-11

Oil stains was observed underneath the drill rig at TST. Contractor shall clear it and provide maintenance works to the plant.

Removal of the contaminated soil and providing the maintenance of the plant

Completion as observed on 26-Oct-11

111020_02

20-Oct-11

Drill rig at TST was located close to the branches of the trees. The plants shall be removed away from the trees.

Protective fence was provided to the trees.

Completion as observed on 26-Oct-11

111026_01

26-Oct-11

The contractor was reminded to tidy up the North gate at HKCEC. As mud was observed exceed the wheel washing facility. Also, sand bag shall be provided or replaced for the gully protection near the site entrance.

Tidy up the North gate at HKCEC and replacement of new sand bags near the site entrance.

Completion as observed on 2-Nov-11

 

8.0.7.        Five site inspections for Contract no. HK/2009/02 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.5.

Table 8.5     Summary of Environmental Inspections for Contract no. HK/2009/02

Item

Date

Observations

Action taken by Contractor

Outcome

110930_01

30-Sep-11

Discarded cement bags shall be covered or disposed properly.

Covering the discarded cement bags

Completion as observed on 6-Oct-11

111006_01

6-Oct-11

Slurry in the U-Channel at ex. Pet Garden shall be removed

Removal of the slurry in U-channel

Completion as observed on 13-Oct-11

111006_02

6-Oct-11

Barrier at two barge shall be maintained to avoid the muddy water spillage to the sea

Maintenance the barrier at the barges

Completion as observed on 13-Oct-11

111006_03

6-Oct-11

It was reminded that a shelter with 3-sides and top shall be provided before the process of grouting works. Besides, the cement bags shall be well covered

Provide a shelter with 3-sides and top for grouting works and well covering the cement bags.

Completion as observed on 13-Oct-11

111013_01

13-Oct-11

Oil Stain was found next to the drip trap at ex. Pet Garden (near Gate 1). Contractor shall clear and dispose of as chemical waste

Removal of the contaminated soil as chemical waste.

Completion as observed on 19-Oct-11

111019_01

19-Oct-11

Floating refuse near eastern seawall shall be removed.

Removal of the floating debris.

Completion as observed on 27-Oct-11

111027_01

27-Oct-11

The contractor was reminded to beware of the silty water after car washing from spilling out to the public road at Gate 2.

Keep maintenance the vehicle washing facilities in proper function

Completion as observed on 3-Nov-11

111027_02

27-Oct-11

Drip tray should be provided to the oil containers near jacking pit.

Providing drip tray underneath the oil containers

Completion as observed on 3-Nov-11

111027_03

27-Oct-11

Protection should be provided to the trees inside the site boundary in front of Harbour Road Sport Centre.

Protective fence was provided.

Completion as observed on 3-Nov-11

8.0.8.        Four site inspections for Contract no. HY/2009/17 were carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.6.

Table 8.6     Summary of Environmental Inspections for Contract no. HY/2009/17

Item

Date

Observations

Action taken by Contractor

Outcome

111012_01

12-Oct-11

Drip tray shall be provided for oil drum storage

Providing drip tray underneath the oil drum

Completion as observed on 19-Oct-11

 

 

Complaints, Notification of Summons and Prosecution

9.0.1.        There was one environmental complaint received on 14 October 2011 for the investigation and follow-up action in the reporting month.

9.0.2.        The complainant, Ms. Tam complained via hotline 1823 about the polluted fumes and exhaust from the excavation by sub-contractor of CEDD on pedestrian way outside no.25 Harbour Road (in front of the Harbour Centre). RSS notified ET to carry out investigation on 17 October 2011.

9.0.3.        The location of the excavator was within site area of Contract no. HK/2009/02 undertaking the water cooling main re-provision works along the Harbour Road. The plants including the excavator have been checked before using at the site. However, the polluted fumes and exhausted from the excavator was caused due to insufficient maintenance of the plant after using at site. After receiving the complaint, the excavator was then removal off-site for checking and maintenance works on 17 October 2011. Contractor was reminded to enhance regular checking and maintenance to all plants at site. RSS has replied to the complainant on the arrangement of the measures taken on 17 October 2011. Complainant was satisfied with the response and follow-up action taken by the Contractor.

9.0.4.        The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.5.        Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

October 2011

1

Sep 10 to September 11

10

Total

11

 

Table 9.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

10.        Conclusion

10.0.1.    The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.    The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1. The construction programmes of individual contracts are provided in Appendix 10.1.

Table 10.1     Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

Contract No.

Key Construction Works

Recommended Mitigation Measures

HY/2009/15

·         Seawall block construction, reclamation work and diaphragm wall construction preparation works at TS4

·         Diaphragm wall construction at TS1 and TPCWAE

·         Night time protection works at CHT

·         Construction of dewatering well at Hung Hing Road and POC

·         Precautionary works at Abutment A

·          Watering any dust generating activities

·          Checking all drip trays frequently and clear any stagnant water and mud inside it.

 

HY/2009/17

·          ELS works for basement construction for pile cap construction.

·          Noise barrier shall be implemented; and

·          Watering any dust generating activities

HY/2009/18

·         Instrumentation Manholes and Intake Culvert Survey

·         Excavation of trial pit

·         Installation of couplers, cable detection, trial trench and pre-drilling in CR3

·         Site investigation and pre-drilling works

·         Diaphragm wall construction

·         Hoarding erection

·          Noise barrier shall be implemented; and

·          Noise level shall be controlled by reducing piling rate and no. of plants working in parallel.

·          Dust control during dust generating works

HY2009/19

·         Marine Pre-drilling

·         Remove existing dolphin

·         Preparation works  and removal of existing marine piles

·         Set up of Contractor’s site office at Oil Street

·         Road works at Watson Road

·         Fabrication of bored piling platform

·         Bored piling

·         Ground contamination  assessment

·         Pre-drilling works for bored pile and Diaphragm wall

·         D-wall Pretreatment

·         Construction of Guide Wall

·          Noise level shall be controlled by reducing drilling rate.

·          Noise barrier shall be deployed for dolphin pier removal.

HK2009/01

·         Diaphragm wall construction works for both CWB and SCL Protection Works within HKCEC 1.

·         Site investigation works at north bank of HKCEC water Channel (from CH 200to CH260).

 

·          Noise level shall be controlled by reducing pilling rate.

·          Well maintain the enclosures for grouting and bentonite mixing plants.

HK/2009/02

·         Tunnel bored pile and diaphragm wall construction works.

·         Toe grout, Shear pine, Pumping test and King Post at WCR1 area.

·          Noise level shall be controlled by reducing pilling rate.

·          Well maintain the enclosures for grouting and bentonite mixing plants.

 

10.0.3.    Construction works of Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A were completed and surrendered on 11 Feb 2011.